MercyOne Clinton Multiple Projects

MercyOne Clinton Linear Accelerator – 13,500sf, January 2020 – November 2020
MercyOne Clinton Pharmacy, Clinton IA – 1,893sf, Feb 2021-Sept 2021
MercyOne Clinton A-Wing, Clinton IA – 6,500sf, April 2021- September 2021

Graham was hired for MercyOne Clinton’s Linear Accelerator Replacement. We worked very closely with the hospital’s physicist to ensure the concrete density and lead shielding requirements were met on the project. Graham’s quality control prior to and during concrete placement ensured that the concrete being placed met all the requirements. At the end of the project, the state completed radiation testing on the vault and it met or exceeded all of the requirements.

The coordination of pouring all the concrete (roughly 2,000 yards in three pours, in a 36’x34’ area, with walls up to 8 ft thick) went seamlessly. Additionally, the equipment coordinator/supplier (Varian, who works with hundreds of contractors a year) said that Graham was one of the few contractors that was fully prepared at all check-in’s and 100% ready for the actual delivery and install.

The renovation of the existing Pharmacy space included demolition and moving existing owner equipment and furniture out of the space and completing the interior fit out. Graham has also worked in their Mercy Living Center North facility, renovating the Lobby, and converting existing rooms in the “A- wing” of the building into exam rooms for various physicians to use.